Welcome Shenzhen FANA CNC Machine Tool Co., Ltd!
Hot keywords: CNC gantry milling machine, gantry machining center, high speed CNC gantry milling machine
Contact us

Shenzhen FANA CNC Machine Tool Co., Ltd

Address: 12b, Shenyun village, Shenyun Road, Nanshan District, Shenzhen

Dongguan factory address: No.2, old airport road, Baisha village, Humen Town, Dongguan City

Tel: +86 0755-29065502

Contact person: +86 13688807582

Email: export@fanacnc.com



Company news
What is your current location:首页>>News Center>>Company news

Inspection of CNC lathe before use

Release time:2018-11-02 16:33:00  Number of views: 254

1. CNC electric box inspection: CNC lathe inspection before use, open the CNC electric box door, check all kinds of interface sockets, servo motor feedback line sockets, spindle pulse generator sockets, manual pulse generator sockets, CRT sockets, etc. if it is loose, plug it in again, and lock it if there is a locking mechanism.

2. Electrical inspection: before use, open the electric control box of the machine tool, check whether the relay, contactor, fuse, servo motor speed, control unit socket and spindle motor speed control unit socket are loose. If they are loose, they should return to normal state. The connector with locking mechanism must be locked, and the socket on the adapter box must be checked for the machine tool with adapter box, If the wiring is loose, it must be locked if there is a locking mechanism.

3. Check the wiring of all buttons, switches and indicator lights on the operation panel. If any error is found, handle it immediately. Check the socket and wiring of CRT unit. The ground wire inspection requires a good ground wire. When measuring the ground wire of CNC lathe, the ground resistance shall not be greater than 1 Ω. Check the phase sequence of the power supply. Check the phase sequence of the input power supply with the phase sequence meter to make sure that the phase sequence of the input power supply is absolutely consistent with that of the power supply calibrated on the machine tool.

4. Inspection of solenoid valve: all solenoid valves shall be pushed by hand several times to prevent bad action caused by long-time power failure. If any abnormality is found, record shall be made for confirmation of repair or replacement after power on.

5. Check the limit switches of CNC machine tools: check the flexibility and fixation of all limit switches, and deal with the problems immediately if the action is bad or the fixation is not firm. Check the buttons and switches on the operation panel,

6. For equipment with secondary wiring, such as power transformer, the consistency of phase sequence of secondary wiring must be confirmed. It is necessary to ensure that the phase sequence of CNC lathe is absolutely correct. At this time, the power supply voltage should be measured and recorded